EPCM
A single managing contractor across engineering, procurement and construction management.
Sectors
In industrial construction the start-up date is set by the process line and equipment deliveries, not by the building. We manage projects in which the construction scope is subordinate to the process.
What is specific
An industrial project differs from a civil one because construction is a supporting activity. What governs the outcome is process sequencing, principal equipment lead times, industrial safety requirements and — on brownfield sites — the need to work without stopping production.
Our sector experience. Delivered and current projects: coke oven batteries and basic oxygen furnace shop facilities inside an operating steel works, a full-cycle automotive plant, a heavy equipment service centre and an oilseed extraction plant.
Risks
Each of these risks is closed by a specific management function.
Principal process equipment carries 6–18 month manufacturing cycles. If those items are not identified and ordered early, delivery sets the start-up date and money cannot accelerate it.
Brownfield means restricted windows, permission for every access, overlap with the production cycle and heightened safety requirements.
Areas cannot be built in arbitrary order: the sequence is fixed by the process, and departures from it cause rework.
High-hazard facilities require documented weld quality, pressure testing and non-destructive examination.
Ramp-up to design capacity requires vendor attendance, staged testing and months that schedules rarely allow for.
A single managing contractor across engineering, procurement and construction management.
Owner-side project management: an integrated team, international methodology, auditable reporting.
Schedule, cost, progress and forecast: a defensible project status every month.
Contractor and work-front coordination, schedule, cost, quality and HSE.
Quality assurance and control, occupational, industrial and environmental safety.
Start-up readiness, commissioning, punch list, statutory handover.
Procurement, tendering, contracts, change orders and claims.
FAQ
Not answered here? Write to us and we will respond on your case.
On an industrial project the start-up date is set by the process line and principal equipment deliveries, not by construction productivity. The civil scope is subordinate to process sequencing, and on brownfield sites to the operating plant's own schedule. Management therefore centres on long-lead procurement and interfaces rather than concrete volumes.
Yes — that is the standard brownfield problem. Works are planned into agreed process windows, every access is cleared with the plant's services, and industrial safety requirements are brought inside the project control loop. At Qarmet in Temirtau we delivered inside an operating integrated steel works without shutting it down.
Technical supervision with certified experts: incoming material inspection, in-process method control, covered-works certification, non-destructive examination of welds and pressure testing. On high-hazard facilities this determines whether the asset may be operated at all.
If it has not started — Project Start-up: WBS, baseline, procurement plan and a long-lead register. If it is running and slipping — a 3–5 week project audit that produces an independent completion date and final cost forecast.

Qarmet JSC

KOMEK Machinery Kazakhstan (Komatsu)

Orbis Manufacturing

Qarmet JSC
Tell us about the asset and the current stage — we will propose a working format and team composition. A commercial proposal follows within five business days of the meeting.
We reply within 1 business day. A commercial proposal follows within 5 business days of the scoping meeting.